|
|
|
|
|
|
 |
|
|
| |
Key
Contract Provisions |
 |
 |
|
| |
Control of risks and claim prevention begins with a thorough
understanding of, and compliance with, key contract provisions
and procedures that address them. Therefore, whether you
are involved as project manager, lead engineer, or in
another way, you must be familiar with all contracts and
subcontracts. For example, before changes to a contract
cost or duration can be authorized, agreement on procedure
for quantification is necessary. Since subcontractors
are often bound by these provisions, a copy of the prime
contract should be provided to major subcontractors. Typical
key provisions include (see glossary for definitions of
specialized terms):
1. Substantial/Final Completion
Project completion should be well defined. In some instances
substantial completion and beneficial use are interchanged.
However, if a project is being beneficially utilized,
the project may be partially substantially complete. Thus
a clear definition of punch list-type activities that
can be done after substantial completion should be included.
Reduction of retainage after substantial completion should
be addressed. A time period should be defined for the
work and providing the documentation required for final
completion.
2. Liquidated/Other Damages
Contracts contain provisions for liquidated damages or
provisions for consequential damages when a contractor
is late in achieving substantial completion (usually).
Some contractors include provisions for no (owner) damages
for delay. Because delay damages may be significant, and
are a major cause of claims, the importance of continually
evaluating schedule risks and timely notification cannot
be overstated.
3. Notification Of Extra Work
Contracts have a variety of clauses requiring the designer
or contractor to notify the owner and/or the designer
of any work that is believed to be extra or outside the
scope of the contract drawing and specifications. The
time frames for notification range from 24 hours to 30
days. It is essential that this be complied with so that
the owner may mitigate the impact, if possible, and the
contractor document its position. Extra work disputes
are also a major cause of claims.
4. Notification Of Delay (Request For Time Extension)
Most contracts require notification of any delay to the
overall project completion date or milestone dates. Time
frames for notification range from 24 hours to 30 days.
It is essential that this also be complied with as above.
5. Differing Site Conditions, Changed Conditions Or
Concealed Conditions
Many construction contracts have some form of provision
to cover the unexpected which is experienced when excavating
a site or opening an existing structure. Because these
are different from extra work that typically improves
the project, unit prices for potential activities should
be included. For example, if soil borings indicate a certain
rock hardness, provisions should be made for the possibility
of discovering harder or more extensive rock. All entities
benefit by having these clauses in the contract, as they
provide a fair solution for what otherwise might be a
difficult problem. Be alert to the notification requirements
and documentation of suitable test results for this type
of change. Along with delays and extra work disputes,
this is also a major cause of claims.
6. Authority Of Parties
The contract should clearly spell out the authority of
the parties to approve change orders and provide for as
much authority at the project level as possible. In addition
to publishing an organizational chart with names and titles
stating responsibilities, it should be clear what change
order amount can be approved by each owner's representative
and how long the authorization process should take. This
is essential for prompt payment for earned work. If this
is not in the contract, a Responsibility Matrix must be
created at the start of a project.
7. Variation In Quantities
The standard clause in many unit price contracts simply
states that if there's a variation in quantities, plus
or minus a certain percentage, both parties will agree
to negotiate a new price. This does not provide for a
resolution of the problem. Equitable contracts specify
a pricing structure for changes for various ranges of
the quantity of work required.
8. Requirements For Progress Schedules
When the owner requires the designer or contractor to
provide a progress schedule, it must be the type of schedule
needed for the project that the people using the schedule
understand. One way for an owner to get the progress schedule
that is needed, on time, is to establish a dollar value
in the contract for submission of that schedule. Lack
of an adequate schedule submission will result in this
dollar value being deducted from requisition. This is
not a penalty. As discussed, all participants need timely
updates of the schedule to resolve issues.
9. Payment Terms
One of the most important clauses to establish in a contract
is the payment terms and the procedures required to obtain
that payment. This should include the definition of stored
material, retention payments, etc.
10. Rates And Markup For Time & Material (T&M) Work
There is always a possibility that a change in the scope
will require work to be performed on a T&M, or cost-plus
basis (sometimes called a force account when a dispute
is involved.) Therefore, it is important that the contract
include not only a clear statement of the rates to be
used for labor and equipment, but also the markup for
overhead and profit to be applied to labor, equipment,
material and subcontract work.
11. Time Limit To Correct (Cure) A Breach
When a party to the contract has breached a "material"
requirement (lack of progress or repeated deficiency that
jeopardizes performance), there should be a time frame
stated (i.e., three days, seven days, etc.) in which the
corrective steps are to be started or completed, or default
may be declared. Default could result in the contractor
being removed from the site with work being completed
by others.
12. Resolution of Dispute
If a dispute cannot be negotiated, the two traditional
possibilities for resolution are arbitration and litigation
(court). Either may be preceded by mediation. There are
pros and cons to arbitration vs. litigation. However,
if arbitration is specified with one party on the project,
the same provision is needed with all other parties on
the project (multi-prime projects). All too often disputes
involve a number of parties on the same project while
a common issue needs to be resolved in a single forum.
Alternate forms of dispute resolution include third party
"neutral" mediation and dispute review boards. Contract
provisions and identification of a third party neutral
mediator or review boards need to be incorporated prior
to signing.
13. Time Limitations For Claim Submission
Most construction contracts clearly state a limitation
on the time frame within which the contractor must submit
a claim. It may be within "X" number of days from when
a change order was rejected, or number of days of completing
the work (which can be vague), or prior to acceptance
of final payment. This must be clearly understood and
strictly complied with.
14. Exculpatory Clauses
Contract exculpatory clauses are used in an attempt to
shift the financial risks for a specified problem from
one party, usually the owner, to another party. The presence
of exculpatory language can create an adversarial relationship
at the start of a job. An example might be "Contractor
is responsible for the risk of all subsoil conditions"
for which the owner has not provided information. These
clauses, which seem to be easy solutions to difficult
problems, often create more problems than they resolve.
15. Ambiguous Contract Language
It is probably impossible to prepare a contract with absolutely
no ambiguity. Words like: reasonable, timely, prompt,
workmanlike, etc. need to be looked at carefully to see
if they can be replaced with more precise language less
open to interpretation by both parties. For example, a
phrase like "the engineer will promptly review shop drawings"
could be more clearly stated as "the engineer will review
and return shop drawings within fifteen work days of their
receipt."
|
| |
|
|
|
|
|