| |
In
the development of a CPM Schedule, either the overall
project duration is known, requiring task durations
and sequencing to complete on time, or the task durations
and sequencing are fixed and the overall duration is
developed manually or by the algorithm in the software.
In order to shorten the overall duration of a project,
critical path activities must be evaluated. Since task
durations depend on resources, resources must be increased
or some tasks must be started before all work of other
tasks is completed.
While each project may be broken into phases, each phase
must be analyzed to identify tasks and the required
resources to complete each task. By so doing, an estimate
of the time for completion may be obtained.
The example WBS and schedule shown in section 6 are
for a project for which detailed design (engineering)
was complete and construction was ready to be awarded.
Even at this stage, however, engineering details or
corrections are part of a project and usually preceded
applicable tasks. As an example, the HVAC, Electrical,
and Plumbing tasks will require, at least, purchase
and manufacturing of components prior to installation.
A more complete WBS and schedule would include these
activities.
The following exercise will allow you to develop a schedule
manually. Table
1 is an example of a WBS with an estimate of resources,
duration, and sequence for each task, for the design
of a new product.
Using this table, develop a Gantt chart, identify the
critical path and estimate the completion date of the
work. In order to prepare a schedule, a calendar is
needed to convert the duration into calendar days. Combining
Table
1 with the calendar results in Table
2. The results are shown in the Product
Design Baseline Schedule.
|
 |