Site Search: search
   
Any project without a schedule understood by all is doomed to failure. Thinking in terms of sequential phases ensures that all decisions are made and all resources are allocated for efficiently moving into each succeeding phase. The previous example was for a Construction Phase schedule. The objectives of scheduling are to:
   
Identify calendar completion dates and constraints.

Identify relationships among various parts of the project.

Determine resource requirements as a function of time.
Identify key points (milestones) where approvals will be needed.
Communicate all of this to all participants and stakeholders.
Maintain good project control.


Scheduling is an iterative process, with a fixed overall duration and adjustments applied to resources and sequencing of tasks to achieve project goals. It is important to note that developing a project schedule often requires input from others. Therefore, the schedule should be a team document with which all participants agree to comply. Simple schedules (with under 25 activities and simple logic as shown in the previous example) can be created without the use of software.

Network diagrams can be used where the logic relationships are not obvious, as in the previous example.

Because networks and schedules are inter-twined, network diagrams (tasks and deliverables shown linked together in the order in which they must be completed) show how the elements of the WBS relate to one another.

   
Superimposing a network on a calendar becomes the basis for creating a detailed project schedule.

Here are some key steps to creating a schedule:
Identify all major events and dates.
Decide in detail and in what sequence WBS tasks need to be done, and develop a network or interrelationship of tasks.
Estimate the duration of each separate activity. Activities should be relatable to the WBS.
Use the activity duration estimates to calculate the estimated project duration.
Identify the time constraints and relate the significance of each activity to the timetable and major events.
Identify resource constraints.