Site Search: search
 
Because projects vary in scope, how resources are applied, and how significant the considerations of timely completion and funding sources are, there are many engineering/business words/terms that are used. The following are incorporated in this Guide.
Baseline - The initial budget and schedule developed to achieve the goals.
Basic Design Package - Further development of Conceptual Engineering to be able to solicit independent confirmation of the project costs and timing (when construction or manufacture is involved).
Conceptual Engineering - Further development of the concept from the Planning Study to arrive at a decision to invest (apply additional resources).
Critical Path - The critical path is, by definition, the subset of activities that must be completed on schedule in order to complete the overall project on time.
Deliverables - A performance standard for each sub-unit or task. Examples are drawings or specifications, or finished products.
Milestones - When depicting a Project Schedule, it sometimes becomes necessary to introduce a milestone in order to preserve the accuracy of the representation. A milestone is a fictitious activity of null duration. It has a cost of zero. However, it does have a reality in that it may not commence before any of its precedents are completed and none of its successors may begin until it has been completed. It is usually reserved to demonstrate a significant event. Examples are "Ready for Testing" or Manufacture.
Network - The interdependencies of the component tasks.
Physical Progress - A measurement of actual items not related to the cost. For example, the number of drawings issued that can be related to the total expected.
Planning Study - The initial technical and financial evaluation of a concept to determine if additional investment in resources is warranted.
Predecessor - An activity that must precede another.
Quality - An attribute that describes an acceptable element of scope or design detail.
Resources - Capital or Human resources.
Scope - The project scope defines technical requirements (systems, equipment, facility requirements) for the product or facility.
Successor - An activity that must follow another.
Work Breakdown Structure - Project activities broken down into sub-units or steps that are of a reasonable duration.