| |
Project
controls are necessary to manage both variances (actual
changes in planned items) and trends (anticipated changes
or risk) for elements of scope, cost and timing. (For
purposes of this Module, scope is defined as the equipment,
materials, and labor required in the design basis, for
a designer, or the design documents, for a contractor,
and the means and methods required to complete the work.)
Because variance and risk management require the elements
of identification, analysis, and attenuation (the minimizing
of potential problems), the focus of project management
must be on communication (and, therefore, understanding)
by each party of the issues and risks involved. Tools
must be in place to evaluate completion progress against
the initial, or "baseline," plan to the satisfaction
of each party.
Identification and analysis of cost and schedule issues
(which often are the result of scope changes) begin
with an evaluation of variances from the baseline plan,
at the smallest definable task. For example, tasks such
as the work of an engineer include the labor means and
methods to develop a drawing, specification, etc. These
tasks can cause problems in timely completion, due to
changes in the scope of work or to the planned design
sequence.
Attenuation requires an understanding of contractual
requirements to rapidly respond to project scope or
other changes, as well as frequent/periodic monitoring
of cost and schedule variances and trends, implementation
of effective safety and quality assurance plans, and
also flexibility in the application of resources. Flexibility
must be built into a project budget (additional contingency
to recover lost time) and schedule (ability to re-sequence
work to recover lost time without increasing costs).
With early application of a "semi-continuous" process
to address positive and negative impacts to budget procurement
activities, the progress of critical tasks, and potential
or pending scope changes, these variances and risks
can be managed. It should be noted that positive variances
are also important because it may be possible to exceed
the goals or provide offsetting allowances as the project
progresses.
The focus of controls is not only on issues, but also
on the timeliness of the decision-making process. To
avert costly delays, issues must be resolved as soon
as possible within a phase, and certainly prior to moving
to the succeeding phase. This is shown via the dotted
line "loop" shown in Figure 1.
|
 |